Views: 0 Author: Sifang Boiler Publish Time: 2015-07-27 Origin: Site
pressure test once
/ The picture shows a corner of the 116MW No. 1 boiler site being installed
The picture shows a corner of the No. 116MW boiler site being installed
On July 23, good news came from the construction site of the 116MW boiler project between our company and Xi'an Hancheng Thermal Power Company. The hydraulic test of the No. 1 boiler of the project was a success!The project manager and on-site installation and construction personnel overcame difficulties such as high temperature, high humidity, and high physical exertion in high-altitude work, and ensured the overall smooth progress of the project according to the time node. So far, more than half of the total project has been completed, and it has received Hancheng Thermal and local special inspections. Department's praise.
It is understood that the No. 2 furnace of the project will undergo a hydraulic test around August 13.The overall progress of the project will be carried out in strict accordance with the contract plan.(Liu Jianmin)